Electrical Energy Infrastructure

  • 35 kV electrical infrastructure comprising of 35 kV/10 kV  substation, 5 km long 35 kV combined line  and 0.8 km long 35 kV cable line  used to supply  the Vinca Integrated Waste Management Centre with electricity and to export electricity produced by the Landfill gas facility.
  • 110 kV electrical infrastructure comprising of 110 kV switchgear, 5 km long 110 kV combined line and  and connection cable and circuit breakers to connect to the Belgrade 20 substation, used for the export of the electricity produced by the EfW facility.