New photos showing the progress made over the previous period.
![default Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-01-1000x563.jpg)
![default Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-02-1000x563.jpg)
![default Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-03-1000x563.jpg)
![Foto dron 150422 04 Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-04-1000x563.jpg)
![Foto dron 150422 05 Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-05-1000x563.jpg)
![Foto dron 150422 06 Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-06-1000x563.jpg)
![Foto dron 150422 07 Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-07-1000x563.jpg)
![Foto dron 150422 08 Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-08-1000x563.jpg)
![default Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-09-1000x563.jpg)
![default Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-10-1000x563.jpg)
![default Construction of Energy-from-Waste facility is ongoing, equipment is delivered, 85% of works have been performed and works on energy plants for energy recovery are underway.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-11-1000x563.jpg)
![default The Construction and Demolition Waste recycling facility started operations in August 17, 2021, with a processing capacity of over 200,000 tons / year](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-12-1000x563.jpg)
![default The Construction and Demolition Waste recycling facility started operations in August 17, 2021, with a processing capacity of over 200,000 tons / year](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-13-1000x563.jpg)
![Foto dron 150422 14 The Construction and Demolition Waste recycling facility started operations in August 17, 2021, with a processing capacity of over 200,000 tons / year](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-14-1000x563.jpg)
![Foto dron 150422 15 The Construction and Demolition Waste recycling facility started operations in August 17, 2021, with a processing capacity of over 200,000 tons / year](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-15-1000x563.jpg)
![default The new sanitary landfill started operations in August 2nd, 2021. Municipal waste collected by PUC Gradska čistoća from the territory of 15 municipalities of Belgrade is disposed of at the new landfill in compliance with the highest waste management standards of the European Union and Serbia. On average, 500 to 600 trucks that is 1,500 tons of municipal waste arrive at the Vinča landfill. Construction of new sanitary cells is ongoing.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-16-1000x563.jpg)
![Foto dron 150422 17 The new sanitary landfill started operations in August 2nd, 2021. Municipal waste collected by PUC Gradska čistoća from the territory of 15 municipalities of Belgrade is disposed of at the new landfill in compliance with the highest waste management standards of the European Union and Serbia. On average, 500 to 600 trucks that is 1,500 tons of municipal waste arrive at the Vinča landfill. Construction of new sanitary cells is ongoing.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-17-1000x563.jpg)
![Foto dron 150422 18 The new sanitary landfill started operations in August 2nd, 2021. Municipal waste collected by PUC Gradska čistoća from the territory of 15 municipalities of Belgrade is disposed of at the new landfill in compliance with the highest waste management standards of the European Union and Serbia. On average, 500 to 600 trucks that is 1,500 tons of municipal waste arrive at the Vinča landfill. Construction of new sanitary cells is ongoing.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-18-1000x563.jpg)
![Foto dron 150422 19 The new sanitary landfill started operations in August 2nd, 2021. Municipal waste collected by PUC Gradska čistoća from the territory of 15 municipalities of Belgrade is disposed of at the new landfill in compliance with the highest waste management standards of the European Union and Serbia. On average, 500 to 600 trucks that is 1,500 tons of municipal waste arrive at the Vinča landfill. Construction of new sanitary cells is ongoing.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-19-1000x563.jpg)
![Foto dron 150422 20 The new sanitary landfill started operations in August 2nd, 2021. Municipal waste collected by PUC Gradska čistoća from the territory of 15 municipalities of Belgrade is disposed of at the new landfill in compliance with the highest waste management standards of the European Union and Serbia. On average, 500 to 600 trucks that is 1,500 tons of municipal waste arrive at the Vinča landfill. Construction of new sanitary cells is ongoing.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-20-1000x563.jpg)
![Foto dron 150422 21 A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-21-1000x563.jpg)
![Foto dron 150422 22 A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-22-1000x563.jpg)
![Foto dron 150422 23 A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-23-1000x563.jpg)
![default A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-24-1000x563.jpg)
![default A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-25-1000x563.jpg)
![default A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-26-1000x563.jpg)
![Foto dron 150422 27 A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-27-1000x563.jpg)
![Foto dron 150422 28 A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-28-1000x563.jpg)
![Foto dron 150422 29 A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-29-1000x563.jpg)
![Foto dron 150422 30 A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-30-1000x563.jpg)
![Foto dron 150422 31 A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-31-1000x563.jpg)
![Foto dron 150422 32 A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-32-1000x563.jpg)
![Foto dron 150422 33 A leachate treatment plant will be put into operation soon to which leachate will be conveyed through a network of pipes and canals, and after treatment it will be discharged into the Osljanski stream, so clean water will flow into the international waterway of the Danube River. Leachate will be treated by reverse osmosis technology.](https://www.bcenergy.rs/wp-content/uploads/2022/04/Foto-dron-150422-33-1000x563.jpg)
New photos showing the progress made over the previous period.
BEO ČISTA ENERGIJA, the Special Purpose Vehicle company, established by ITOCHU Corporation (Japan), VEOLIA Group (France) and Marguerite, a pan-European infrastructure investor (Luxembourg), successfully commenced on July 1, 2024 the full scope of Services in accordance with the Public-Private-Partnership contract with the City of Belgrade.
Check the drone video of July 1st, 2024.
Mr. Bosko Maravic ESHS Manager, participated today in the round table “ESG Challenges”, alongside Ms.Senka Jelenkovic from Belgrade Airport, Mr. Nicolas Marquier from IFC, Mr. Antoine Avignon from the EU delegation, and moderator Ms. Stevan Pechitch.